Indian Hills High School Window Replacement

This project is currently being designed by Dicara Rubino Architects.

 Anticipated milestones:

Award Bid – end of January

Shop drawings March submitted to architect

Shop drawings approved April

April –July – window fabrication

August 3rd - Start of construction

October 2nd - Substantial completion

October 30th - Final completion.


Bids received January 16, 2020 - Currently under attorney review.